Temple de la Fusterie
POSE DES BRIQUES DE TERRE COMPRESSEE AU SOUS-SOL / JUILLET 2026
CLOCHER APRES DEMONTAGE DE LA FERBLANTERIE EN ECAILLES / JUIN 2026
ECHAFAUDAGES INTERIEURS EN COURS DE MONTAGE
COMBLES APRES DETUILAGE / MAI 2026
POSITIONNEMENT DES ARMATURES SOUS LA CHAIRE / MAI 2026
ETAYAGE DE LA DALLE DE LA NEF AVANT BETONNAGE / MAI 2026
ECHAFAUDAGES EXTERIEURS FINALISES / MAI 2026
DETUILAGE ET SUPPRESSION DES LATTAGES DETERIORES / MAI 2026
DETUILAGE DE LA COUVERTURE DE LA NEF EN COURS / MAI 2026
CLOCHER AVEC FERBLANTERIE EN ECAILLES / MAI 2026
ARMATURES DE LA DALLE DE COMPRESSION AVANT BETONNAGE / MAI 2025
POSE DU PLANCHER EN BOIS MASSIF / MARS 2026
EXPERTISE DES TUILES SUR LE TEMPLE / MARS 2026
POSITIONNEMENT DES SOMMIERS SUR LA SECONDE MOITIE DU TEMPLE / FEVRIER 2026
PAVAGE DES POURTOURS DU TEMPLE AVANT REALISATION DES ECHAFAUDAGES EXTERIEURS / NOVEMBRE 2025
BETONNAGE DE L'ETAPE 1 DE LA DALLE DE COMPRESSION / NOVEMBRE 2025
REALISATION DE LA TREMIE DE L'ESCALIER DROIT / SEPTEMBRE 2025
REALISATION DU PLANCHER BOIS / AOÛT 2025
FIXATION DES SOLIVES SUR LES SOMMIERS EN BOIS MASSIF (EPICEA PROV. VALAIS) / JUILLET 2025
SCIAGE DES PALPLANCHES AU PLASMA AVANT REMBLAIS / JUIN 2025
PREPARATION DES COLONNES AVANT POSE DES SOMMIERS / JUIN 2025
ASSEMBLAGE DES SOMMIERS SUR SITE / JUIN 2025
SCIAGE EN ATELIER ET MONTAGE A BLANC DE LA CHARPENTE / MAI 2025
NETTOYAGE DU TEMPLE AVANT POSE DU PLANCHER DE LA NEF / AVRIL 2025
REALISATION DU MUR D'ECHIFFRE DE L'ESCALIER / MARS 2025
DEMONTAGE DU TREUIL DE LEVAGE / MARS 2025
AJUSTEMENT DES MURS DE FONDATION POUR POSE PLANCHER BOIS DE LA NEF / FEVRIER 2025
SORTIE DE LA PELLE MECANIQUE / FEVRIER 2025
COMBLEMENT DES CAROTTAGES / JANVIER 2025
COFFRAGE DERNIERE ETAPE DE REMONTEE RADIER / DECEMBRE 24
REALISATION RADIER ETAPE D'ANGLE / OCTOBRE 2024
REPRISE EN SOUS-OEUVRE ANGLE SUD-EST / SEPTEMBRE 2024
VUE GENERALE / AOÛT 2024
EXCAVATION SOUS FONDATIONS PARTIE MEDIANE SUD-OUEST / AOÛT 2024
EXCAVATION SOUS FONDATIONS PARTIE MEDIANE SUD-OUEST / AOÛT 2024
EXCAVATION SOUS FONDATIONS PARTIE MEDIANE SUD-OUEST / AOÛT 2024
BETONNAGE RADIER - ETAPE 1 / JUILLET 2024
ARMATURES RADIER / JUILLET 2024
SURPROFONDEUR DES FOSSES POUR MONTE-CHARGE ET VENTILATION / JUIN 2024
AMEUBLISSEMENT ET TERRASSEMENT / MAI 2024
EXCAVATION POUR REPRISE EN SOUS-OEUVRE / AVRIL 2024
TRAVERSES HAUTES POUR REPORT DES CHARGES MURS PORTEURS SUR MICROPIEUX / MARS 2024
TERRASSEMENT INTERIEUR / FEVRIER 2024
CEINTURAGE HAUT POUR STABILISATION DE L'ENCEINTE DE L'EDIFICE / JANVIER 2024
CAROTTAGE POUR MISE EN PLACE DES TRAVERSES HAUTES / DECEMBRE 2023
PASSAGE DES TRAVERSES DANS LES FONDATIONS DES FAÇADES / NOVEMBRE 2023
FORAGE DES PUITS D’ÉPUISEMENT DES EAUX / OCTOBRE 2023
CAROTTAGE SOUS LA FONDATION DE LA CHAIRE / SEPTEMBRE 2023
DEGAGEMENT DES FONDATIONS COLONNES / AOÛT 2023
PASSAGE DES TRAVERSES DANS LES FONDATIONS DES COLONNES / JUILLET 2023
DEBUT DU TERRASSEMENT DANS LA NEF / JUIN 2023
RÉALISATION DES MICROPIEUX INTÉRIEURS / MAI 2023
VIBROFONÇAGE DES PALPLANCHES / MARS 2023
ESSAIS DE MISE EN CHARGE DES MICROPIEUX / FÉVRIER 2023
FORAGE DES MICROPIEUX D’ESSAI / DECEMBRE 2022
DÉMOLITION DU MUR DERRIERE LA CHAIRE / NOVEMBRE 2022
DÉMOLITION DU RADIER / OCTOBRE 2022
PROTECTION DE L‘ESPACE PUBLIC / MAI 2022
DÉMENAGEMENT DES BANCS / FEVRIER 2022
DÉMENAGEMENT DES GRADINS / FÉVRIER 2022
DÉMONTAGE DE L’ORGUE / OCTOBRE 2021